Brite Hellas S.A. is currently working on an investment project partially funded by a grant from Iceland, Liechtenstein and Norway through the EEA Financial Mechanism 2014-2021, in the frame of the Program “Business Innovation Greece”, grant reference number ProSol 2021/580905. In the course of this project, Brite will develop a manufacturing line for its nanocoated semi-transparent panel technology. The line will be built in an industrial building space leased by Brite in the Industrial Zone of Patras, Greece.
Required Production Tools
The line equipment should be entirely derived from production tools that are commercially available now. The key material deposition tool is the ink-jet printer.
The flow of the production line
The steps in the production of solar glass are shown in the diagram below:
Mass production process requirements
The design of the line for mass production of Brite Solar has the following requirements:
Όλα όσα πρέπει να γνωρίζει ένας αρχάριος για τα Διαδικτυακά Καζίνο
- Achievement of mass production with existing tools on the market.
- Low cost of the line and hence small cost of depreciation in the value of the final product.
- The highest possible production throughput of solar glass, which can be augmented with tools or be repeated, to increase the total production. A minimum of 1 million m2 / year of solar glass should be supported.
- The production line must fit to an open floor industrial space of no more than 6.000 m2.
- The power required to operate the line shall not exceed 1 MWp including support equipment such as electrical lifts etc.
- The target for the line yield is above 90% and for its availability a minimum of 11 months per year. These parameters should be used to calculate the line throughput at a minimum.
- The line should support fully automated traceability of stage testing for the produced modules. The test data should be available to both Brite and the customer for the produced panels, and the information should be stored in the panel itself.
The received quotes/proposals will be evaluated within 4 weeks of the closing date. Non-selected proposals can submit an appeal within 3 days from the time of notification of the evaluation result. All quotes should refer to RFQ: ProSol 1 and be submitted electronically to:
All questions or other inquiries concerning this quote should be addressed to the point of contact for this procurement who is:
Dr. Nick Kanopoulos
+30 6943461393